Construction QA/QC Checklist: Checks and Evidence for Every Stage and Trade

By , President and CEO, YelloSKYE. Published .

Close-up of an open steel stud wall at first fix under work lights, two electrical back boxes and clipped cable runs in view, with a thin yellow line joining the tops of the boxes before the wall is boarded

Executive Summary

  • The Question: What should a construction QA/QC checklist contain at each stage of a building project, and what proof should each check leave behind?
  • The Answer: A usable checklist is organised by stage and by trade, and every line states the pass condition, who inspects and which evidence gets filed. The tables below cover pre-construction, substructure, frame, envelope, MEP, finishes and handover, plus a quick card for each key trade.
  • The YelloSKYE Angle: Construct IQ supplies much of that evidence: dated drone, 360°, fixed-camera and laser-scan captures in the DEX platform, with issues tagged directly on the site visual.

A construction QA/QC checklist is a list of the checks each element must pass before work moves on, with the acceptance condition for each check and the evidence to keep. The version below is organised by build stage and then by trade, so you can copy the relevant tables into your own inspection test plan and adjust tolerances to your specification. Every line names the proof to record, because a tick with nothing behind it is hard to defend later.

This page is the checklist itself. For why inspection points sit where they do and how hold and witness points work, read our guide to construction quality control. Much of the evidence listed here can come from routine site capture through Construct IQ, YelloSKYE's construction monitoring solution.

How to read the tables

Each stage table has four columns: the check, the condition that counts as a pass, the inspection type, and the evidence to file. Tolerances are written as "as specified" on purpose: use the figures in your own specification and standards, not generic ones.

Inspection type

Code Meaning on this checklist
S Self-check by the trade, recorded before calling the main contractor
W Witness: inspector notified and may attend
H Hold: work stops until a named person releases it
R Review of records, on site or from the office

Evidence codes

Code What to file
P Dated photos: one wide shot that shows where you are, one close-up of the detail
360 A 360° walk of the area along the project's standard capture route
LS Laser scan, registered and compared with the design model
DR Drone capture: orthomosaic, elevation imagery or survey data
M Measurement record: levels, dimensions, readings, with the instrument used
T Test result or certificate, referenced to the exact element or system
SIG Name, role and date of the person who accepted the work

Every completed check should also carry a short header: location (level, zone, gridline or room), drawing and specification revision, trade, inspector and date. Our guide to construction site inspections explains each of these fields in more detail.

Stage 1: Pre-construction set-up

These are quality assurance checks. Nothing is built yet, but most later failures trace back to a gap here.

Check Pass when Type Evidence
Quality plan issued Every stage has a named inspector and a deputy R Signed plan, distribution list
ITP for each trade package Every covering activity has a check directly before it R ITP register with revision
Drawing control Site sets match the current revision register R Dated register extract
Material submittals Approved before ordering; samples stored on site H Approval record, P of samples
Mock-ups and benchmark areas Standard agreed by designer and owner H P and 360 of the mock-up, SIG
Existing conditions Site, neighbouring buildings and services recorded R DR, P
Survey control Control points set out and independently checked W M, coordinate listing
Capture plan Route, frequency and who captures are agreed R Capture schedule

Stage 2: Substructure

Almost everything here is buried within days, so most checks are hold points.

Check Pass when Type Evidence
Formation level and bearing Levels and ground as designed, base not softened by water H M, DR or P, geotechnical sign-off
Piles Position, depth and integrity as specified H Pile log, T, as-built positions (M)
Below-ground drainage Falls, bedding and joints correct; test passed H T, P, M
Waterproofing or tanking Laps continuous; corners and penetrations detailed; no damage H P per detail, 360 of each wall
Foundation reinforcement Bar sizes, spacing, cover, laps and starter bars as drawn H P, M, SIG on pour release
Ground slab preparation Membrane, insulation and service stubs in position H 360 or P, M
Backfill Approved material placed and compacted in layers W T (compaction), P

Stage 3: Frame

The pour is the big covering event. Record the deck fully before concrete arrives.

Check Pass when Type Evidence
Formwork Line, level, plumb, stable and clean S, W M, P
Reinforcement Matches drawings; spacers give the specified cover H P, 360 or LS before the pour
Cast-in items Sleeves, embeds, anchor bolts and conduits match the coordinated model H LS or 360, M
Concrete delivery Approved mix confirmed, samples taken W Delivery tickets, T
Curing and striking Method and striking times as specified S Curing log
Post-pour survey Slab levels, column positions and openings within tolerance R LS, M
Structural steel Connections complete, bolts marked as tightened, alignment checked H P, M, T
Masonry Wall ties, movement joints and lintels in place W P

Where tolerances are tight, a scan beats a tape. On YelloSKYE's as-built versus BIM clash detection work, a terrestrial laser scan taken after a structural stage is overlaid on the design model in Revit or Navisworks, so a misplaced column or missing sleeve is found before follow-on trades start.

Stage 4: Envelope

Check Pass when Type Evidence
Brackets and fixings Type, spacing and embedment as designed H P per bay, T (pull-out tests)
Air and vapour control layers Continuous, taped and sealed at every junction H P, 360
Cavity barriers and insulation Positioned as drawn, no gaps H P per elevation zone
Windows and doors Installed, packed and sealed; drainage path clear W P, T (water test)
Cladding Panel alignment, joint widths and fixings as specified S, R DR elevation capture, M
Roofing Substrate, falls, laps, upstands and outlets correct H DR, P, T (leak test)
Sealants Correct product on prepared joints S P

Elevations are slow to check from the ground. A facade inspection from a desk uses a dated high-resolution map of each elevation in DEX, with the elevation drawing laid over it, so reviewers can measure and mark issues before deciding what needs a close-up visit.

Stage 5: MEP installation

Check Pass when Type Evidence
Routing and clearances Services follow the coordinated model W 360, LS
Supports and brackets Type and spacing as specified S P
Electrical first fix Containment, back boxes and cables positioned and segregated S, W 360 before boarding
Pipework pressure tests Test held for the specified duration with no loss H T referenced to system and zone
Ductwork leakage tests Within the specified limit H T
Insulation and labelling Complete and readable S P
Fire stopping at penetrations Approved system, complete, labelled H P of each penetration, register
Commissioning Systems perform to the design W T (commissioning sheets)

Stage 6: Finishes and fit-out

Check Pass when Type Evidence
Partitions before closing Services tested, backing for fixtures and acoustic insulation in place H 360 of each room
Board and joint finish Flatness and joints as specified S P
Screed Level, thickness and moisture content suitable for the floor finish W M, T
Wet areas Waterproofing complete and tested before tiling H P, T (flood test)
Ceilings Grid level; access panels where the services need them S, W 360
Joinery and fittings Securely fixed and operating S P
Decoration Matches the approved sample S P beside the mock-up record
Protection Finished work protected from following trades S P

On YelloSKYE's interior fit-out projects, 360° walks are captured by ordinary site staff with no specialist technician, and each image is mapped to its place on the floor plan. Teams reported 70% less coordination time and snags closing five times faster.

Stage 7: Handover

Check Pass when Type Evidence
Contractor's own zone inspection Every zone walked and defects recorded R 360 per zone
Punch items Each item closed against a photo of the fix R P before and after, SIG
Test and commissioning file Every system has its certificates R T index
Manuals and warranties Complete for every installed product R Document register
As-built information Drawings or model updated to what was built R LS, M
Visual record Owner and operator have access to the full capture history R Access confirmation
Defects period plan Reporting route and response times agreed R SIG

How to run the closeout list itself is covered in our construction punch list guide. On the warehouse operator handover use case, the operator was given role-based access to the full visual history in DEX at completion, and there were no documentation disputes after handover.

Trade cards

Stage tables follow the building. Trades work across several stages, so give each trade its own short card. Pin these into the subcontract package and ask for the evidence column at every hand-over between trades.

Trade Before starting Before work is covered Evidence the trade hands over
Concrete Formwork accepted; mix approved; pour plan agreed Reinforcement, cover and cast-ins released (H) Pour release, delivery tickets, cube or sample results
Structural steel Foundation bolts surveyed; erection sequence agreed Connections inspected before fire protection Bolt check record, weld tests, P of connections
Waterproofing and roofing Substrate dry, clean and accepted Every lap, corner and penetration inspected (H) P per detail, leak or flood test
Electrical Routes coordinated; containment drawings current First fix recorded before boarding 360 of each room, test schedules
Mechanical and plumbing Routes coordinated; supports agreed Pressure or leakage test passed (H) T per system and zone, 360
Fire stopping Approved systems listed for each penetration type Every penetration sealed and labelled (H) P and register entry per penetration
Drylining and ceilings Services above and behind signed off Room recorded before boards go on (H) 360 of each room, P of backing
Finishes Substrate accepted; samples approved Not applicable: inspect on completion P against mock-up, snag list

What counts as good evidence

The evidence column is only useful if someone can find and trust it later. Apply these rules to every type.

Evidence Good enough when
Photo The wide shot shows a gridline, door or other fixed reference; the close-up includes a tape or scale where size matters
360° walk Taken on the same route each time and placed on the floor plan, so two dates can be compared
Laser scan Registered to project coordinates and compared with the model, with the deviations reported
Drone capture Dated, covering the whole area being checked, and comparable with the previous flight
Test certificate Names the system, the zone and the test standard, and is filed with the check it supports
Measurement States the instrument, the reading and the specified tolerance

Where an issue is found, raise it on the record rather than in a message. Construct IQ uses geo-referenced annotations, so a non-conformance is tagged directly on the site visual and the contractor sees exactly where and what needs fixing. DEX also lets reviewers scroll back through the site history day by day, which helps when a fix needs to be compared with the original condition.

Non-conformance log: the columns to keep

Column Example entry
Reference NCR-L3-014
Location Level 3, gridline C/4, riser cupboard
Check it failed Fire stopping at penetrations
Description Two cable trays unsealed through the compartment wall
Evidence P (wide and close), 360 capture of the riser
Owner and due date Fire stopping contractor, before ceiling closure
Corrective action Seal with approved system and label
Closure evidence P from the same position, SIG of verifier
Root cause noted Trade briefing missed cable tray detail

The last column is where QC feeds QA. If the same root cause appears on several floors, change the method or the briefing, not just the defect.

Adapting this checklist to your project

  1. Copy the stage tables that apply. A fit-out job may only need Stages 1, 5, 6 and 7.
  2. Replace "as specified" with real numbers. Pull tolerances, test durations and limits from your specification.
  3. Check the inspection types against your quality plan. Add hold points wherever your contract or authority requires attendance.
  4. Name people, not roles. Each H line needs a person who can release it the same day.
  5. Match the evidence to your capture routine. Time 360° walks and scans to the covering events, not to a fixed weekday.
  6. Issue the trade cards with the subcontracts. Trades should know what evidence they owe before they mobilise.
  7. Review the non-conformance log weekly and update the checklist when a fault repeats.

Frequently asked questions

What should a construction QA/QC checklist include?

Each line should name the check, the condition that counts as a pass, the type of inspection (self-check, witness or hold) and the evidence to file. The header should record the location, the drawing revision, the inspector and the date. Without the acceptance condition and the evidence, a ticked box proves very little.

How do I create a QA/QC checklist for my project?

Start from the specification and the inspection test plan for each trade package, then list every activity that will hide or lock in earlier work and put a check immediately before it. Use a generic stage checklist, like the one in this guide, as a starting point and add the project's own tolerances, tests and approvals. Review it with each trade before they start.

What evidence should be recorded for a QA/QC check?

Record at least a dated photo showing where the element is and a close-up showing the detail being checked. Add measurements, test certificates or a scan where the check depends on a number. Before a covering activity, a full 360° walk or scan of the area is worth keeping because it shows conditions nobody thought to photograph.

Should subcontractors fill in their own QA/QC checklists?

Yes. Each trade should self-check its work against the checklist and attach evidence before asking the main contractor to inspect. The main contractor then verifies, and hold points are released by the person named in the quality plan. Self-checking catches most faults early and shortens the formal inspection.

Is a paper QA/QC checklist good enough?

Paper can work on a small job, but it is hard to search, easy to lose and rarely linked to photos or locations. A digital checklist that stores the evidence with each line, pinned to a place on the drawing, is far easier to audit later and to share with the owner and designers.